{"id":8929,"date":"2017-10-30T13:15:49","date_gmt":"2017-10-30T12:15:49","guid":{"rendered":"https:\/\/www.wg-a.com\/?p=8929\/"},"modified":"2017-11-24T12:32:03","modified_gmt":"2017-11-24T11:32:03","slug":"baufortschritt-hauptbahnhof-c-18-b-3-2","status":"publish","type":"post","link":"https:\/\/www.wg-a.com\/en\/baufortschritt-hauptbahnhof-c-18-b-3-2\/","title":{"rendered":"Construction progress Hauptbahnhof C.18.B"},"content":{"rendered":"<p>Construction progress Hauptbahnhof C.18.B 30.10.2017<\/p>\n<p>Meanwhile the shell reached the last floor and so the final structure of the building is now more and more recognizable.<br \/>\nThe finishing elements for the ceiling above the third floor are for the most part moved and partially also concreted.<br \/>\nSo the first walls could be built on the fourth floor in the area of stairway 1 .<br \/>\nAlso a sample window was already installed on the first floor.<\/p>\n<p>Indoors the first preparations for the dry construction are being made. The future positions for kitchen are already visible because of the slots for the associated connections.<br \/>\nThe entire shell should be completed in November.<\/p>\n<p>&nbsp;<\/p>\n<p><a href=\"https:\/\/www.wg-a.com\/en\/projects\/hauptbahnhof-c-18-b-bloch-bauer-promenade-21-vienna\/\">&lt;&lt;see project&gt;&gt;<\/a><\/p>\n","protected":false},"excerpt":{"rendered":"<p>Construction progress Hauptbahnhof C.18.B 30.10.2017 Meanwhile the shell reached the last floor and so the final structure of the building is now more and more recognizable. The finishing elements for the ceiling above the third floor are for the most &hellip; <a href=\"https:\/\/www.wg-a.com\/en\/baufortschritt-hauptbahnhof-c-18-b-3-2\/\">Continued<\/a><\/p>\n","protected":false},"author":4,"featured_media":8923,"comment_status":"open","ping_status":"open","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"footnotes":""},"categories":[38],"tags":[],"class_list":["post-8929","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-construction-progress"],"acf":[],"_links":{"self":[{"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/posts\/8929","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/users\/4"}],"replies":[{"embeddable":true,"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/comments?post=8929"}],"version-history":[{"count":8,"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/posts\/8929\/revisions"}],"predecessor-version":[{"id":8938,"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/posts\/8929\/revisions\/8938"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/media\/8923"}],"wp:attachment":[{"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/media?parent=8929"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/categories?post=8929"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/www.wg-a.com\/en\/wp-json\/wp\/v2\/tags?post=8929"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}