The drywall work is at various stages of completion throughout the building’s different sections and floors. The first floor shows the work’s greatest degree of completion. The plumber is installing the necessary ventilation and sanitary pipes in the riser shafts. Additionally, the pipes for the kitchen facilities and the Kemper valves are installed on the balconies, either on the exposed ceiling or in designated floor conduits. At the same time, the plumbing connections for the sinks and washbasins are being installed. The electrician is setting up distribution cabinets for the residential units. In section A, we have installed fall protection in the first areas of the balconies.