Construction progress Weinzingergasse

Baufortschritt Weinzingergasse

Construction progress Weinzingergasse 22.02.2019 The excellent weather conditions at the construction site allowed not only the ceiling above the cellar but also the first walls of the ground floor to be completed. The firewalls with semi-finished parts are elevated parallel … Continued

End of construction Grundäckergasse

Baufertigstellung Grundäckergasse

End of construction Grundäckergasse 19.02.2019 In cooperation with STRABAG and Mischek ZT GmbH, the new plant was completed in time after a construction period of 20 months and handed over to the client. On behalf of the Bank Austria Real … Continued

Award for the project Aspern J12, Vienna

Award for the project Aspern J12, Vienna On Thursday, February the 14th, 2019 the project Aspern J12 got awarded by ÖGNB and klimaaktiv Bauen und Sanieren within the BauZ! Congress at the Exhibition Grounds in Vienna. Stefan Cerwenka, head of … Continued

Construction progress Viktringer Ring, Klagenfurt

Construction progress Viktringer Ring, Klagenfurt 15.02.2019 The building structure continues to grow tremendously. By now the ceiling above the 3rd floor was mostly concreted. As a result, only two more floors remain to be finished in the upcoming weeks. What is … Continued

Construction progress Hauptbahnhof C.16.D

Baufortschritt Hauptbahnhof C.16.D

Construction progress Hauptbahnhof C.16.D 15.02.2019 The construction work on building site C.16.D in the Sonnwendviertel is making great progress. The building structure of the cellar and the ground floor, where a business establishment will be located in the future, have … Continued

Construction progress Miriam-Makeba-Gasse

Baufortschritt Miriam-Makeba-Gasse

Construction progress Miriam-Makeba-Gasse 12.02.2019 After the start of construction in October 2018, the work in the basement has already been completed. The walls and columns on the ground floor have been constructed and the slab above the ground floor is … Continued

Construction progress Grundäckergasse II

Baufortschritt Grundäckergasse II

Construction progress Grundäckergasse II 31.01.2019 Before the end of the year, the structure for the first construction phase was already in place. The remaining building components are close to being completed and the entire architectural ensemble is already clearly noticeable, … Continued

Construction progress Weinzingergasse

Baufortschritt Weinzingergasse

Construction progress Weinzingergasse 24.01.2019 During the first weeks, several walls in the basement were already built. In addition, the construction of the concrete infill in the selected bored pile sections started and the building pit stiffeners were partly removed according … Continued

Construction progress Parking deck Oberwart

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Parking deck Oberwart 23.01.2019 The first phase of the structural work is complete! The dismantling of the construction crane has already started. All installed supports, prefabricated balustrades, hollow planks and hollow walls form the completed shell of the … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 22.01.2019 The construction work on all three construction sites is progressing rapidly. The construction work has been completed at site 2 and the apartments were handed over to the owners. At construction site 1, the … Continued