Construction progress Saltenstrasse

Baufortschritt Saltenstrasse

Construction progress Saltenstrasse 14.12.2018 The double parking garage pits are completely finished. They have been sealed, the working areas sealed again and the cleanliness layer concreted. The base slab of the basement is now placed on top and the concrete … Continued

Construction progress Hofwiesengasse

Construction progress Hofwiesengasse 13.12.2018 After relocating the streetcar station and setting up the construction site, work was ready to start. The drilled piles were completed and the pile grids were essentially completed. Starting from Lainzer Strasse, the construction pit excavation … Continued

Construction progress Viktringer Ring, Klagenfurt

Baufortschritt Viktringer Ring, Klagenfurt 12.12.2018

Construction progress Viktringer Ring, Klagenfurt 12.12.2018 The height of the building continues to rise steadily. In the meantime, the walls on the 1st floor have been completed and the concreting of the upper ceiling started. Although the concrete slab is … Continued

Construction progress Stadlbreiten 9+11

Baufortschritt Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 29.11.2018 The construction work is progressing at full speed. The facades of stairs 2 and 3 are already completely finished and the framework is almost dismantled. The plumbing work in the attic and roof areas is … Continued

Construction progress Weinzingergasse

Baufortschritt Weinzingergasse

Construction progress Weinzingergasse 24.11.2018 The digging work is progressing very well, so that the crane foundation could be started in the rear area. In the meantime, the connecting pipes for the in-depth drilling and the ditch for the double parking … Continued

Construction progress Saltenstrasse

Baufortschritt Saltenstrasse

Construction progress Saltenstrasse 16.11.2018 After the digging, the brine pipes were laid and the related collecting shaft was already connected and concreted. After that, the soil was compacted again and in the deeper areas, for the double park facilities, the … Continued

Construction progress Parking deck Oberwart

Parkdeck Oberwart

Construction progress Parking deck Oberwart 15.11.2018 Since the ground-breaking ceremony on October, 2nd, 2018, the construction work is now progressing rapidly. After the digging, the quiver and strip foundations for the prefabricated components lying above were manufactured. Since all external … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 14.11.2018 The construction work is progressing very well on all three sites. The work on construction site 2 is completed and the apartments were already handed over to the building owners. The construction work is … Continued

Construction progress Hauptbahnhof C.16.D

Baufortschritt Hauptbahnhof C.16.D

Construction progress Hauptbahnhof C.16.D 13.11.2018 We have made a good start – the crane is standing and the construction pit is secured. As only minor digging work was necessary on this site, the foundation work has already started. At the … Continued

Tokyo – trip 2018

Tokyo – trip 2018 At the end of October a part of the WGA team departed for Tokyo. As part of an architecture seminar, the vibrant metropolitan region with its impressive skyscrapers was visited. The works of Kenzo Tange, in … Continued