Construction progress Saltenstrasse

Baufortschritt Saltenstrasse

Construction progress Saltenstrasse 17.04.2019 The ceiling above the cellar is completely concreted, the garage ramp is installed, most of the walls on the ground floor are set up and even the first ceiling section above the ground floor is finished. … Continued

Construction progress Parking deck Oberwart

Baufortschritt Parkdeck Oberwart

Construction progress Parking deck Oberwart 12.04.2019 All steel beams, light purlins and trapezoidal sheets were installed, so the roof is now completed. Now that the concrete has already been laid, it will soon be possible to start coating the surfaces … Continued

Construction progress, Cityquartier Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 12.04.2019 The construction work on sites 1 and 3 is progressing rapidly. On site 2, which has already been handed over, the spacious gardens will be individually designed by the new owners at the beginning … Continued

Topping-out ceremony Grundäckergasse II

Topping-out ceremony Grundäckergasse II 11.04.2019 The topping-out ceremony was celebrated with a good spirit in the community garage. The representatives of the two building owners DWK and RIKAG and the general contractor PORR AG thanked all workers and planners involved … Continued

Construction progress Paulusgasse

Baufortschritt Paulusgasse

Construction progress Paulusgasse 11.04.2019 The building has really risen since the last construction progress report. The structural work is almost ready and the windows are installed up to the 4th floor. All the interior work is in progress and the … Continued

Construction progress Grundäckergasse II

Baufortschritt Grundäckergasse II

Construction progress Grundäckergasse II 04.04.2019 The building structure was completed on time for spring-time. A building element of the first construction phase already made its appearance with a completed exterior facade. The facades of the other buildings are gradually being … Continued

Construction progress Stadlauer Strasse

Construction progress Stadlauer Strasse 27.03.2019 Thanks to the magnificent weather, the construction work is progressing rapidly. The 1st basement is almost finished and parts of the ground floor are already visible. Because of the work of three cranes and about 70 … Continued

Construction progress Miriam Makeba-Gasse

Baufortschritt Miriam-Makeba-Gasse

Construction progress Miriam Makeba-Gasse 27.03.2019 This construction site is continuously rising in height and the completion of the building structure is almost achieved. At the present time, the ceiling above the 3rd floor is in the process of being formed and … Continued

Site Visit Grundäckergasse I+II

Site Visit Grundäckergasse I+II 22.03.19 On March 22, 2019 we made use of the sunny Friday afternoon to visit our most recently completed project in Grundäckergasse 16-20 and to check out the current status of the very close project in … Continued

Construction progress Weinzingergasse

Baufortschritt Weinzingergasse

Construction progress Weinzingergasse 22.03.2019 The entire team is happy after having completed the exhausting cellar work. Now the above-ground floors of the structural building are being lifted up one after the other. In the meantime we reached the walls on … Continued