Construction progress Educational Campus Aron Menczer, Vienna

Construction progress Educational Campus Aron Menczer, Vienna 08.08.2019 A few months ago, the construction work for the Aron Menczer educational campus in Adolf-Blamauer-Gasse started. In an area of approximately 17,000 m², the foundation pits were secured for the time being … Continued

Construction progress Paulusgasse

Construction progress Paulusgasse 01.08.2019 The construction work in the Paulusgasse is now close to its final phase and one can also see how the workers give their very best to complete the joint project. The roof is already sealed and … Continued

Construction progress Viktringer Ring, Klagenfurt

Construction progress Viktringer Ring, Klagenfurt 30.07.2019 By now almost all of the facade is completed. Only a few areas have to be finalized in order to round up the facade. In addition, the roof construction started, the ventilation unit was … Continued

Construction progress Weinzingergasse

Construction progress Weinzingergasse 26.07.2019 The interior work reached the next milestone with the closure of the drywalls. Afterwards, the fill was added and the installation of the floor heating system started. After these preliminary works, the pavement will be laid … Continued

WGA barbecue afternoon

WGA barbecue afternoon 17.07.2019 On Friday, July the 17th of 2019 we had a great barbecue afternoon in our garden even though the temperatures were very hot. In a relaxed atmosphere, time flew by with our traditional grill specialities and … Continued

Construction progress Saltenstrasse

Construction progress Saltenstrasse 17.07.2019 In the last month, the building structure has grown again upwards with another two floors. A good rhythm was established so that the construction work is progressing rapidly. The deliveries of the various materials are, of … Continued

End of construction (phase 1) Parking deck Oberwart

End of construction (phase 1) Parking deck Oberwart 12.07.2019 The first phase of the parking deck was completed in cooperation with STRABAG AG as the general contractor. On behalf of Burgenländische Krankenanstalten GmbH, a total of 314 parking spaces were … Continued

Construction progress Aspern J4

Construction progress Aspern J4 11.07.2019 During the last weeks of summer people not only were swimming in Seestadt but they also worked a lot. The two lower building components B1 and B2 reached the top floor in the meantime, while … Continued

Construction progress Cityquartier, Wiener Neustadt

Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 08.07.2019 The work on the construction site 1 is finished and the entire building unit was handed over to the client. In cooperation with STRABAG AG as the general contractor, 89 apartments and an underground … Continued

Construction progress Hofwiesengasse

Construction progress Hofwiesengasse 02.07.2019 We are continuing to work on the building structure, even in the extremely hot weather. The top storey is currently under construction for structural element 1, the walls have been finished and the first roof panels … Continued