Construction progress Messestrasse II

Baufortschritt Messestrasse II

Construction progress Messestrasse II 30.11.2017 The shell is growing fast! Component 1 reached the planned high, component 2 is nearly as high as it supposed to be and in the component 3 there are still a few floors left to … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 28.11.2017 Since the official start of construction on 27.02.2017 the construction work on plot 2 is progressing rapidly. In the area of staircases 1, 2 and 3 the construction of the walls on the 3rd … Continued

Construction progress Wagramer Strasse

Baufortschritt Wagramer Strasse

Construction progress Wagramer Strasse 24.11.2017 In part 1, the windows were completely installed and the drywall work is progressing rapidly. In the lower floors, the underfloor heating has started to be installed; soon the screed can be made here as … Continued

Topping-out ceremony Aspernstrasse 115

Gleichenfeier Aspernstrasse 115

Topping-out ceremony Aspernstrasse 115 23.11.2017 The roof has been reached at Aspernstrasse 115. This occasion was celebrated on 23.11.2017 together with two other projects of the developer Hart + Hart. Representatives of Hart + Hart developers, Auböck Baugesellschaft, WGA ZT … Continued

Construction progress Eckertstrasse

Baufortschritt Eckertstrasse

Construction progress Eckertstrasse 23.11.2017 The façades for the residential floors are mostly complete. The areas of the building site still being used for storage or where work is continuing are gradually getting smaller and smaller, scaffolding and construction equipment are … Continued

Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 23.11.2017 The topping-out ceremony is already in sight! At the beginning of next week, the concrete for the last ceiling above the 4th floor will be delivered and the shell completed in succession. The roof terrace … Continued

Construction progress Aspern J12

Construction progress Aspern J12 22.11.2017 According to the construction schedule, the exterior facade of component 1 and component 2 has been completed and the outside railings have now been completely painted. The interior fittings (drywall, electrical and domestic engineering installations) … Continued

Business Breakfast – Strabag Real Estate

Strabag Real Estate invited on Tuesday the 14th of November 150 guests from the local real-estate industry for a business breakfast on the 19. floor the “Sky-Stage” in the Tech Gate Vienna. Harald Oissner the managing partner of WGA ZT … Continued

Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 13.11.2017 The construction on Anschützgasse is progressing rapidly. Except for a few apartments, the screed works are completely completed. The double floor is already being laid on the office floors. The radiators are already installed. Sanitary rooms … Continued

Los Angeles – trip 2017

wga zt

From 26.10.-3.11.2017 a delegation from WGA was able to discover the architecture of Los Angeles and look at it in detail. Alongside outstanding cultural buildings like the Getty Center, LACMA, Walt Disney Concert Hall or The Broad, the programme also … Continued