Construction progress Stadlbreiten 9+11

Baufortschritt Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 29.11.2018 The construction work is progressing at full speed. The facades of stairs 2 and 3 are already completely finished and the framework is almost dismantled. The plumbing work in the attic and roof areas is … Continued

Construction progress Weinzingergasse

Baufortschritt Weinzingergasse

Construction progress Weinzingergasse 24.11.2018 The digging work is progressing very well, so that the crane foundation could be started in the rear area. In the meantime, the connecting pipes for the in-depth drilling and the ditch for the double parking … Continued

Saltenstrasse 1, Vienna – Construction progress

Baufortschritt Saltenstrasse

After the digging, the brine pipes were laid and the related collecting shaft was already connected and concreted. After that, the soil was compacted again and in the deeper areas, for the double park facilities, the surface layer and the … Continued

Construction progress Parking deck Oberwart

Parkdeck Oberwart

Construction progress Parking deck Oberwart 15.11.2018 Since the ground-breaking ceremony on October, 2nd, 2018, the construction work is now progressing rapidly. After the digging, the quiver and strip foundations for the prefabricated components lying above were manufactured. Since all external … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 14.11.2018 The construction work is progressing very well on all three sites. The work on construction site 2 is completed and the apartments were already handed over to the building owners. The construction work is … Continued

Construction progress Hauptbahnhof C.16.D

Baufortschritt Hauptbahnhof C.16.D

Construction progress Hauptbahnhof C.16.D 13.11.2018 We have made a good start – the crane is standing and the construction pit is secured. As only minor digging work was necessary on this site, the foundation work has already started. At the … Continued

Tokyo – trip 2018

At the end of October a part of the WGA team departed for Tokyo. As part of an architecture seminar, the vibrant metropolitan region with its impressive skyscrapers was visited. The works of Kenzo Tange, in his various creative periods, … Continued

Aspern J4, Vienna – Construction progress

Baufortschritt Aspern J4, Wien

This week we had the opportunity to view the construction site from the crane. This gave us a perfect overview of the construction progress and gave us an idea of the dimensions of the finished project. Meanwhile, the ceiling above … Continued

Gailenbachweg 5, Salzburg – Construction progress

Baufortschritt Gailenbachweg

Thanks to the beautiful autumn weather, construction work on the old length of the mill in Salzburg is progressing rapidly, so that a second crane has already been placed on the construction site. The concreting of the first foundation slabs … Continued

Construction progress Paulusgasse

Baufortschritt Paulusgasse

Construction progress Paulusgasse 06.11.2018 Work on the construction site is very busy. The cellar walls have been completed and the installation of the ceiling reinforcement above the cellar is in full swing. In the back area of the property, the … Continued