In component A, work on the screed is in progress in several residential units. This is carried out once the drywall and door frames have been fully installed, and the electrical and domestic installations for each residential unit have been completed. The elevator has also been installed in this component. At the same time, the required chimney outlets and shaft tops are being installed on the roofs, and the railings are being mounted in the stairwells. At the same time, the window assemblies in component B have been completed. The first sunshade panels have been installed, and the interior installation is progressing, as is component A. Meanwhile, the assembly of the first windows has begun in component D, and the installation of the post-transom facades is progressing on the ground floor of the overall project. At the same time, the work on the shell construction in component C is almost finished.