Construction progress Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 21.08.2017

The shell has now been made up to the walls on the first floor. At the moment, the formwork, reinforcement and concrete work on the ceiling takes place over the first floor. It is easy to see how the conductors of the component activation are laid over the first reinforcement plane.

The walls on the ground floor are completely shut off and the visible concrete floor is finished. Only the pillars made of exposed concrete retain their formwork as a protection from soiling until the end of the shell work.

The retaining wall in the garden is completely finished and the backfill is completed down to the area under the crane. Furthermore, the house canal was constructed up to the connection to the road channel.

 