Bildungscampus Aron Menczer, Vienna – Construction progress

The construction work is progressing rapidly.  The floor panel and walls on the ground floor are mostly finished. At the moment the ceiling above the ground floor has been completed and the casing and strengthening for the walls on the 1st floor is being prepared. Some of the walls have already been concreted. In the following weeks, the ramp construction work will start, which will initially be integrated into the educational campus and will later be transformed into a freestanding walkway. This should offer an attractive linkage to the Fasanviertel which is separated by the railway line. At the same time, the construction of the access tower for the ramp with a staircase and an elevator in the north of the building site will start.

 