Gailenbachweg 5, Salzburg – Construction progress

The construction work around the old mill site has started. As a first step, the excavation pit was partially excavated. Then it was time to secure the excavation pit by means of embankments and to set the sheet pile walls. A special jet blasting method is used to secure the excavation pit around the existing mill building. The first crane has already been placed and the concreting of the foundation of the underground car park can be started soon. We are looking forward to the future development of the construction project.

 