Construction progress Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B  20.12.2017

The year 2017 is coming to an end and the crane on construction site Hauptbahnhof C.18.B can be dismantled on schedule even before the new year starts.
All of the roof domes have been put up completely and even the installation of the windows is already about 80% complete. All of the exposed concrete ceiling in Top17 staircase 2 was struck last week. Meanwhile work on the drywall on the residential floors is going flat out. The paneling on one side of the 2nd floor will be completed this week. The moisture barrier on the roof is complete and the first gradient insulation will even be laid before Christmas. In the basement the screed has been laid and the ceiling soffit has also been insulated.

The construction site will shut down from 22.12.2017 to 8.1.2018 for its well-earned Christmas break. On this note we wish everyone happy holidays and a prosperous new year!

 

<<see project>>