Leopoldauer Strasse 72, Vienna – The casing works have already started

In order to make the construction work for the new residential complex at Leopoldauer Strasse 72 easier, the site was divided into three sections.The first section is located on Ichagasse. Here the exterior walls are already in place and the casing work for the ceiling above the 2nd basement level is currently in progress. It is expected that this ceiling will be finished concreting at the beginning of next week. On the second part of the site, which is located on Kendegasse, the ceiling of the 2nd basement level is also shuttered at the same time. The inner walls and columns will be concreted in the third and middle part of the site. Here the outer walls are expected to be finished by the end of the week.

<<see project>>