Rugierstrasse 55, Vienna – Construction progress

The installation work on the collection pipes for the geothermal energy was fully finalised. After that, the different shafts were installed, reinforced and concreted underneath the base plate. Following these preparations were successfully carried out, the first area of the base plate was already installed. Subsequently, the second section is now being placed and, parallel to this, the first basement walls are under construction.

 

<<see project>>