Rugierstrasse 55, Vienna – Construction progress

All the walls and the ceiling above the basement floor have been completely concreted. Also, the steel-concrete work on the ramp is already finished. Then all the walls of the ground floor have been set up and the casing and the reinforcement construction work of the first ceiling above the ground floor have started. The building is now rising floor by floor upwards, with the courtyard area always being built first and afterward the street area. At the same time, the shafts of the garden areas were also concreted, so that the waterproofing above the basement can already be installed there.

 