Construction progress Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 11.06.2018

As planned in the construction schedule, the shell of the building is nearing completion. While work is still in progress on the ceiling above the first attic floor in staircase 1, this is already complete in staircase 2. At staircase 3 some hollow walls of the second attic floor are already concreted. The painters are already working and are filling walls and ceilings.
At the same time the raw installation was started.