Construction progress Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 23.08.2018

During the hot summer weather the roofs were sealed and the first windows were installed. At the same time, the carpenters are also working on the wooden roof structures including the skylights. While the installation work can be carried out in component 3, the drywall walls are already finished in component 2. In component 3, the filling is introduced into the first apartments and the scaffolding is completed on the facade.

<<see project>>