Construction progress Weinzingergasse

Construction progress Weinzingergasse 28.10.2019

On all surfaces the plaster facade is completed and after that the anti-drop protection and the window sills were installed. This means that the facades have been constructed in such a way that the scaffolding can be dismantled very soon. At the same time, the paneling between the balconies is installed and the railings on the roof terraces are mounted.  Meanwhile, the tiling work inside the building has started at full speed, whereby the floors on the first two floors have already been set. The other coverings and fittings will now be installed gradually for each apartment.

<<see project>>