Construction progress Weinzingergasse

Construction progress Weinzingergasse 24.10.2018

The ten deep boreholes for the future heating system have already achieved the final depth of approx. 150 metres. At the same time, the pile grid was built, allowing the work to begin immediately after the removal of the drilling equipment. The straps for the construction pit bracing have also already been relocated, so that in the next step the steel bracing is mounted and the digging is advanced to its planned level.

 