Cumberlandstraße 38, Vienna – Construction work is in full swing

On the northern façade, the installation of the steel construction of our acoustic protection wall is currently progressing rapidly and has already been partially completed. At the same time, the construction of the drywall on the sixth floor is proceeding in the same part of the building.

Meanwhile, in the north-eastern section, the first sun protection panels have been installed, which will ensure a particularly comfortable indoor climate during the summer.

In the southern section, the construction of the walls on the first floor was completed. These walls form the basis for the construction of the floor above. In addition, some walls on the third floor have already been concreted in some sections.