Construction progress Wagramer Strasse

Construction progress Wagramer Strasse 02.02.2018

In both components, the drywall construction work has been completed and the floor heating and screed have been completely installed on all floors. The crane was removed and the recess in the foundation plate was closed. Parts of the wall and ceiling insulation have already been installed in the garage. The portals in part 1 were installed and the bases for the garden fence were also manufactured. Painting work has begun in the apartments. In part 2, the wall and floor tiles were laid. The work on the composite thermal insulation system is in full swing.

 

<<see project>>