Excavation to the required levels took place in the first construction phase. The foundation areas were marked during the surveying process and indicated by markings in the surrounding terrain. Compliance with the target heights is monitored continuously during excavation. The next step is to install a rolling element as a capillary-breaking and separating layer. Cleanliness layers are then prepared, and reinforcement work is carried out in preparation for subsequent concreting.