Omega Haus, Offenbach am Main – Further progress in the construction work

The Omega House interior finishing work is once again in full swing. All the suspended luminaires in the sample zone have already been installed. Based on this, the lighting scheme of the office areas, which is oriented to the façade grid, becomes apparent. In addition, all cooling ceiling elements have been hung in the band grid. The sanitary rooms in this area have already been tiled. In Building B, drywall construction and TGA installation work is currently in progress on floors 1-6. The roofing work on the flat roofs of Building Parts B and C is still in full swing. In Building C, the structural work is in its final stages.

<<see project>>