Omega Haus, Offenbach am Main – In the past couple of weeks, a lot has been happening on the construction site

Currently, steel structures of various sizes are being installed to reinforce the existing ceilings in the area of the subsequent wall and ceiling openings. The installation work has already started in building section A. The location of the future shafts for the sanitary units can already be anticipated on the basis of the vertical risers that have already been installed. At the same time, the first interior plastering work is taking place in the future office spaces. The dismantling work is continuing to progress rapidly. Currently, the drywall, the floors, and the ceilings in sections B and C are being dismantled.