News

End of construction Paulusgasse

End of construction Paulusgasse 12.12.2019 With joy, we proudly announce that the project at Paulusgasse was completed on 11/18/2019. Together with Lieb Bau Weiz GmbH & Co KG as the general contractor, the Haring Group Bauträger GmbH was responsible for … Continued

Construction progress Paulusgasse

Construction progress Paulusgasse 24.09.2019 The scaffolding on the street side of Paulusgasse was already removed and now the facade shines in full splendour! Inside the courtyard, the facade work is currently being completed. The floor surfaces in many apartments were … Continued

Construction progress Paulusgasse

Construction progress Paulusgasse 01.08.2019 The construction work in the Paulusgasse is now close to its final phase and one can also see how the workers give their very best to complete the joint project. The roof is already sealed and … Continued

Paulusgasse 15, Vienna

Project information

Procedure
Selection procedure
Client
Haring Group Bauträger GmbH
Doningasse 12, Stiege 1, 2. OG, Top 05
1220 Vienna
Principal
Haring Group Bauträger GmbH
Doningasse 12, Stiege 1, 2. OG, Top 05
1220 Vienna
Address
Paulusgasse 15, 1030 Vienna
Start of planning
06/2016
Start of construction works
05/2018
Completion
11/2019
Construction costs
6,50 Mio. (netto)
Size of order
Overall planning

Videos

On the 1080m² site at the crossroads Paulusgasse/Schlachthausgasse, a building is being built on two different building classes with a total of 66 residential units and about 3360m² of living space. The residential house consists of compact 2-3 room apartments, which are oriented towards the street and/or the inner courtyard.

The residential units on the ground floor are aligned to the green inner courtyard and have a private garden. The apartments on the upper floors each have a balcony or a loggia, which are accessible from the living room and thus allow the connection to the outside space. The attic apartments are also equipped with spacious terraces. The house is accessed via a central staircase and by a barrier-free lift for eight people.

Garbage, bicycle and baby carriages are located on the ground floor. There is also a spacious children’s playroom in the garden. In the lower floor are the necessary car parking spaces as well as storage and technical areas and another bicycle room.