Construction of the project commenced at the end of March and work is progressing rapidly. The deep drilling has been completed successfully and the preliminary excavation of the construction pit has already started. The production of the bored piles started … Continued

Primary School Laaer Berg, Vienna

Project information

Procedure
Selection procedure
Client
STRABAG AG Direktion AR Hochbau Wien
Donau-City-Straße 9
1220 Vienna
Principal
STRABAG AG Direktion AR Hochbau Wien
Donau-City-Straße 9
1220 Vienna
Address
Laaer-Berg-Straße 170, 1100 Vienna
Start of planning
07/2023
Start of construction works
03/2024
Completion
08/2025
Construction costs
-
Size of order
Architecture planning

As a result of the increasing number of primary school pupils, a school extension has been planned for the existing location at 170 Laaer-Berg-Strasse in the 10th district of Vienna. One of the goals was to harmonise the spatial and functional programme with the ideas of the users as well as with the official and technical specifications and to design the existing building with the extension as a coherent unit that made sense in terms of its functions.

The central spatial element on the ground floor is the multifunctional assembly hall. The entrance area with seating steps to the existing building as well as the dining hall and the library have been designed as an open, multifunctional area. There is a large entrance loggia in the open space outside the multifunctional assembly hall. This covered area serves as an entrance area and weather-protected outdoor area where the pupils can spend time. The transparent design of the façade between the assembly hall and the entrance loggia allows for an intensive connection to the outside space. The gymnasium and the movement room have been designed right next to each other in the basement.

The stairs and the lift lead up to the top floor so that the roof area can be used for school purposes. A pergola construction with solar panels is planned on the roof, which will provide a canopy and natural shading at the same time.