Obersteinergasse 11, Vienna – Construction progresses

Construction at Obersteinergasse 11 is progressing according to plan. All windows, French doors as well as lift-and-slide doors have already been installed. The screed is being laid in the attics.The preparations for the tiling work on the first floors are … Continued

Schäffergasse 10-12, Vienna – Plumbing work on the roof

The construction work in Schäffergasse 10-12 continues diligently. All windows and French doors have been installed together with the sun protection. The screed work has already been completed on the first four upper floors. The installation of the thermal insulation … Continued

Obersteinergasse 11, Vienna – Screed work starts

After the topping-out ceremony at Obersteinergasse 11, work quickly resumed. Now screed work is starting on the ground floor. The French windows and lift-and-slide doors have already been installed on the ground floor, on the first floor and at the … Continued