Aspern J4, Vienna – Construction progress

Because of the good weather in the last few weeks, the construction work in Seestadt is progressing well .The excavation pit support is largely completed, the first sections of the base plate are concreted and the cranes have grown to … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 16.06.2018 The construction work is making good progress on all three construction sites. On lot 2, in the area of staircases 1, 2 and 3, the installation of the external facade insulation is completed and … Continued

Construction progress Messestrasse II

Construction progress Messestrasse II 05.07.2018 Our locksmiths are fully committed! The expanded metal facade is being installed and the future appearance can already be anticipated. The locksmiths are also active inside. So the assembly of the railing has started in … Continued

Construction progress Paulusgasse

Baufortschritt Paulusgasse

Construction progress Paulusgasse 21.06.2018 The progress of the work in the construction pit is examined in the Paulusgasse during beautiful weather. After the construction of the excavation pit support has been almost completed, the preparations for the setting up of … Continued

Construction progress Wagramer Strasse

Baufortschritt Wagramer Strasse

Construction progress Wagramer Strasse 12.06.2018 The construction work on Wagramer Strasse is almost complete and the owners will soon be able to move into their apartments. The facade was completely plastered and painted. The scaffolding on the facade of component … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 11.06.2018 On all three construction sites the construction work is progressing rapidly. On lot 1, in the area of staircases 1, 2 and 3, the installation of the external facade insulation is almost complete and … Continued

Construction progress Stadlbreiten 9+11

Baufortschritt Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 11.06.2018 As planned in the construction schedule, the shell of the building is nearing completion. While work is still in progress on the ceiling above the first attic floor in staircase 1, this is already complete … Continued

Construction progress Messestrasse II

Baufortschritt Messestrasse II

Construction progress Messestrasse II 08.06.18 The building is taking shape inside and outside. The windows are mounted, the substructure for the expanded metal façade is available and the ETICS façade is installed. Painted walls, suspended ceilings, laid parquet and tiled … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 07.05.2018 Since the official start of construction, construction work on all three building sites has been proceeding rapidly. On site 1, in the area of staircases 1, 2 and 3, the production of the coffin … Continued