Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 07.05.2018 Since the official start of construction, construction work on all three building sites has been proceeding rapidly. On site 1, in the area of staircases 1, 2 and 3, the production of the coffin … Continued

Construction progress Aspern J12

Construction progress Aspern J12, 1200 Vienna 07.05.2018 Building element 1 and building element 2 were handed over to the owner in January and the majority of the apartments have already been settled. The final work has already been completed on … Continued

Construction progress Messestrasse II

Baufortschritt Messestrasse II

Construction progress Messestrasse II 27.04.18 After the Topping-out ceremony, work is once again carried out on the construction site. The thermal bonding system is attached to the facade, windows and mullion-transom facade are diligently installed, plasterboard walls are placed, porcelain … Continued

Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B 27.04.2018

Construction progress Hauptbahnhof C.18.B 27.04.2018 Nature is blossoming and the house on lot C.18.B is already shining in the most beautiful colours, because the thermal insulation composite facade in the inner courtyard is plastered. The mullion and transom facade on … Continued

Construction progress Stadlbreiten 9+11

Baufortschritt Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 17.04.2018 Thanks to the beautiful spring days, the shell work is progressing well. The walls of all components were completed on the first floor. For building components 2 and 3, the slabs on the first floor … Continued

Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 12.04.2018 The construction work in Anschützgasse is entering its final phase and completion is approaching. The final completion work is currently being carried out in the interiors and the existing facade on Anschützgasse will soon be repainted. … Continued

Construction progress Wagramer Strasse

Baufortschritt Wagramer Strasse

Construction progress Wagramer Strasse  29.03.2018 Step by step the completion in the Wagramer Strasse is approaching and the first results of the interior work are visible. The insulation under the ceiling was completely installed in the underground car park. The staircase … Continued

Construction progress Wenhartgasse

Baufortschritt Wenhartgasse

Construction progress Wenhartgasse 28.03.2018 Due to the better weather conditions now, clearly visible progress could be made in the construction of the outdoor facilities. The garden fences and paths have already been built and work is underway on the interior … Continued

Construction progress Stadlbreiten 9+11

Construction progress Stadlbreiten 9+11 27.03.2018 After the basement ceiling was completed, the walls on the ground floor could be constructed. The slabs above the ground floor of building elements 1 and 2 have already been concreted. In component 3, the … Continued

Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 26.03.2018 Spring is only beginning to get going this year, while our drywall construction work on the office floors is already well under way. Most of the walls are planked on one side and the concrete … Continued