Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 30.10.2017 Meanwhile the shell reached the last floor and so the final structure of the building is now more and more recognizable. The finishing elements for the ceiling above the third floor are for the most … Continued

Construction progress Aspern J12

Baufortschritt Aspern J12

Construction progress Aspern J12 In accordance with the construction schedule, the exterior facade, analogue to component 2, is finished in the residential building of component 1, and the exterior wings are now painted. The interior construction (drywall, electrical and building … Continued

Construction progress Messestrasse II

Baufortschritt Messestrasse II

Construction progress Messestrasse II 23.10.2017 In some areas is the shell already on the 5th floor. After the pre-stressed ceiling has cured over the future large auditorium on the ground floor, the work in component 3 will also proceed quickly. … Continued

Construction progress Wagramer Strasse

Baufortschritt Wagramer Strasse

Construction progress Wagramer Strasse 23.10.2017 The interior construction (drywall, electrical and building services installations) in component 1 is in full swing. The first drywall walls already form the rooms in the individual dwellings and the units are slowly taking shape. … Continued

Construction progress Cityquartier, Wiener Neustadt

Baufortschritt Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 23.10.2017 The construction work on property 2 progresses rapidly. The floor slab and the cellar walls are completely built. Meanwhile the construction of the walls on the first floor has been completed in the area … Continued

Construction progress Anschützgasse

Baufortschritt Anschützgasse

Construction progress Anschützgasse 02.10.2017 The construction work at Anschützgasse is progressing rapidly. All drywall walls were placed in the office floors. The wet cells are already tiled. The lift has also been installed and the electrical and building services are … Continued

Construction progress Wenhartgasse

Baufortschritt Wenhartgasse

Construction progress Wenhartgasse 27.09.2017 The ceiling above the last attic floor has been concreted, also the shell of the driveway is already finished. Therefore was the crane this week dismantled. On the first floor the drywallers are almost finished with … Continued

Construction progress Hauptbahnhof C.18.B

Baufortschritt Hauptbahnhof C.18.B

Construction progress Hauptbahnhof C.18.B 27.09.2017 Despite the autumn weather the work on the construction site is progressing. The formwork for the walls on the second floor has almost been completed. A large part of the reinforced concrete walls on this … Continued

Construction progress Cityquartier, Wiener Neustadt

Construction progress Cityquartier, Wiener Neustadt 26.09.2017 The floor slab and the cellar walls have already been completely erected. In the area of the stairways 1, 2 and 3, the construction of the ground floor walls has now been completed. In … Continued

Construction progress Aspern J12

Baufortschritt Aspern J12

Construction progress Aspern J12 25.09.2017 In accordance with the construction schedule, the outer facade, similar to component 2, has now also been completed in the residential building of component 1. The interior design (dry construction, electrical and building services installations) … Continued